Volume 2, Issue 1 — Year 2025 — Article e100032

ISSN (Online): 3115-8129 Biannually

Prioritization of Influencing Factors on Interactive Role of Consulting-Contractors in Advancing Project Goals

Article Type: Research
Pages: e100032
DOI: https://doi.org/10.22034/CGEL.2.1.e100032

Authors
Affiliations
  1. Department of Civil and Construction Management, Binaloud Institute of Higher Education, Mashhad 9351991949, Iran
  2. Department of Civil and Construction Management, Binaloud Institute of Higher Education, Mashhad 9351991949, Iran
  3. Department of Civil and Construction Management, Binaloud Institute of Higher Education, Mashhad 9351991949, Iran
Corresponding author
Email: f.sanaz@gmail.com
Received: 13 March 2025 / Accepted: 8 May 2025 / Published: 20 May 2025
Abstract

Civil projects play a critical role in shaping urban landscapes over time, serving as visible and enduring social structures. Given their public visibility, meticulous attention to planning and design stages is crucial. Collaboration among project stakeholders is a primary driver of success. Regular progress review meetings are essential, not only to monitor advancement but also to implement timely corrective and preventive measures. Continuous updates to project plans enhance the likelihood of successful completion. Supervision by specialized engineers ensures the safety and quality of constructed structures. This study employs the Analytic Hierarchy Process (AHP) to evaluate the interactive dynamics between consulting engineers and contractors, based on inputs from 217 experts involved in five urban projects in Mashhad, Iran. Pairwise comparison questionnaires were used for data collection, and analyses were conducted using ExpertChoice and SPSS software. The findings identified five main criteria (bid documents, consultant-contractor contracts, consultant requirements, contractor performance, and environmental conditions), along with 21 sub-criteria. Among these, bid documents were deemed the most influential, with a 53.7% weight, underscoring their significance in shaping consultantcontractor interactions. Contracts ranked second at 23.2%, emphasizing the economic and unilateral perspectives often prevalent in project execution. Environmental conditions, with a minimal 3.6% influence, were the least impactful, as they are typically integrated into contractors' operational designs. Overall, the study highlights the pivotal role of enhancing consultantcontractor collaboration in achieving project success.

Keywords

Civil projects, Consultant-contractor collaboration, AHP model, Bid documents, Project success

Data availability statement

The data supporting the findings of this study are available within article. No publicly archived dataset was generated.

Funding

This research received no external funding.

Highlights
  • Consultant and contractor collaboration affects project success
  • Bid documents are the most critical factor
  • AHP evaluates key interaction criteria effectively
References
  1. Abed M., Alhalaq K., Tayeh B.A., Abed M. (2018). Selecting the appropriate construction contract type by using the analytical hierarchy process approach. International Journal of Construction Project Management, 10(2), 137.
  2. Abeysinghe N., Jayathilaka R. (2022). Factors influencing the timely completion of construction projects in Sri Lanka. Plos One, 17(12), e0278318. https://doi.org/10.1371/journal.pone.0278318.
  3. Acheamfour V.K., Kissi E., Adjei-Kumi T. (2019). Ascertaining the impact of contractors pre-qualification criteria on project success criteria. Engineering, Construction and Architectural Management, 26(4), 618-632. https://doi.org/10.1108/ECAM-03-2018-0110.
  4. Agbo A.A. (2010). Cronbach's alpha: Review of limitations and associated recommendations. Journal of Psychology in Africa, 20(2), 233-239.
  5. Aghazadeh E., Yildirim H. (2021). Assessment the effective parameters influencing the sustainable materials selection in construction projects from the perspective of different stakeholders. Materials Today: Proceedings, 43, 2443-2454. https://doi.org/10.1016/j.matpr.2021.02.280.
  6. Akbari A., Feili A., Dashtipour M. (2022). Identifying and prioritizing arising claim's factors by the combined approach of DEMATEL and ANP method (case study: urban development and civil organization of shiraz municipality projects). Journal of Soft Computing in Civil Engineering, 6(1), 46-65. https://doi.org/10.22115/scce.2022.288877.1328.
  7. Akintoye A., Main J. (2007). Collaborative relationships in construction: the UK contractors' perception. Engineering, Construction and Architectural Management, 14(6), 597-617. https://doi.org/10.1108/09699980710829049.
  8. Al Saadi A.M.D., Rahman I.A. (2019). Identification of delay factor in Oman construction industry. International Journal of Sustainable Construction Engineering and Technology, 10(1), 34-45. https://doi.org/10.30880/ijscet.2019.10.01.004.
  9. Alavi M., Kayworth T.R., Leidner D.E. (2005). An empirical examination of the influence of organizational culture on knowledge management practices. Journal of Management Information Systems, 22(3), 191-224. https://doi.org/10.2753/MIS0742-1222220307.
  10. Al-Harthi A.S., Soetanto R., Edum-Fotwe F. (2014). Revisiting client roles and capabilities in construction procurement. School of Civil and Building Engineering, Loughborough University, Loughborough, UK.
  11. Allen I.E., Seaman C.A. (2007). Likert scales and data analyses. Quality Progress, 40(7), 64-65.
  12. Alsugair A.M. (2022). Cost deviation model of construction projects in Saudi Arabia using PLS-SEM. Sustainability, 14(24), 16391. https://doi.org/10.3390/su142416391.
  13. Amireh F. (2022). A study on the impact of contractor selection method and contractors’ pre-qualifications on delays in Jordanian public construction projects. Doctoral dissertation, University of Bedfordshire, Luton, England.
  14. Atout M.M. (2016). Delays caused by project consultants and designers in construction projects. International Journal of Structural and Civil Engineering Research, 5(2), 102-107.
  15. Belay S., Goedert J., Woldesenbet A., Rokooei S. (2022). AHP based multi criteria decision analysis of success factors to enhance decision making in infrastructure construction projects. Cogent Engineering, 9(1), 2043996. https://doi.org/10.1080/23311916.2022.2043996.
  16. Blayse A.M., Manley K. (2004). Key influences on construction innovation. Construction Innovation, 4(3), 143-154. https://doi.org/10.1108/14714170410815060.
  17. Boone Jr H.N., Boone D.A. (2012). Analyzing likert data. The Journal of Extension, 50(2), 48. https://doi.org/10.34068/joe.50.02.48.
  18. Brown D.C. (2003). A methodology for selecting the construction team. Doctoral dissertation, University of Southampton, England.
  19. Bujang M.A., Omar E.D., Baharum N.A. (2018). A review on sample size determination for Cronbach’s alpha test: a simple guide for researchers. The Malaysian journal of medical sciences, 25(6), 85.
  20. Bygballe L.E., Jahre M., Swärd A. (2010). Partnering relationships in construction: A literature review. Journal of Purchasing and Supply Management, 16(4), 239-253. https://doi.org/10.1016/j.pursup.2010.08.002.
  21. Çalişkan E., Aksakal E., Çetinyokuş S., Çetinyokuş T. (2019). Hybrid use of Likert scale-based AHP and PROMETHEE methods for hazard analysis and consequence modeling (HACM) software selection. International Journal of Information Technology & Decision Making, 18(05), 1689-1715. https://doi.org/10.1142/S0219622019500330.
  22. Chan A.P.C., Scott D., Chan A.P.L. (2004). Factors affecting the success of a construction project. Journal of Construction Engineering and Management, 130(1), 153-155. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(153).
  23. Dadzie J., Abdul-Aziz A.R., Kwame A. (2012). Performance of consultants on government projects in Ghana: client and contractor perspective. International Journal of Business and Social Research, 2(6), 256-267.
  24. Dai J., Goodrum P.M., Maloney W.F., Srinivasan C. (2009). Latent structures of the factors affecting construction labor productivity. Journal of Construction Engineering and Management, 135(5), 397-406. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:5(397).
  25. Doloi H., Iyer K.C., Sawhney A. (2011). Structural equation model for assessing impacts of contractor's performance on project success. International Journal of Project Management, 29(6), 687-695. https://doi.org/10.1016/j.ijproman.2010.05.007.
  26. Egemen M., Mohamed A.N. (2005). Different approaches of clients and consultants to contractors’ qualification and selection. Journal of Civil Engineering and Management, 11(4), 267-276. https://doi.org/10.1080/13923730.2005.9636357.
  27. Elsayah O.S. (2016). A Framework for Improvement of Contractor Selection Procedures on Major Construction Project in Libya. Doctoral dissertation, Edinburgh Napier University, Edinburgh, Scotland.
  28. Kamal A., Abas M., Khan D., Azfar R.W. (2022). Risk factors influencing the building projects in Pakistan: from perspective of contractors, clients and consultants. International Journal of Construction Management, 22(6), 1141-1157. https://doi.org/10.1080/15623599.2019.1683693.
  29. Kaufmann A., Tödtling F. (2001). Science–industry interaction in the process of innovation: the importance of boundary-crossing between systems. Research Policy, 30(5), 791-804. https://doi.org/10.1016/S0048-7333(00)00118-9.
  30. Kometa S.T., Olomolaiye P.O., Harris F.C. (1994). Attributes of UK construction clients influencing project consultants' performance. Construction Management and Economics, 12(5), 433-443. https://doi.org/10.1080/01446199400000053.
  31. Kshaf D.A., Mohamed M.A., El-Dash K.M. (2022). The major problems between main contractors and subcontractors in construction projects in Egypt. Ain Shams Engineering Journal, 13(6), 101813. https://doi.org/10.1016/j.asej.2022.101813.
  32. Kumaar A.N., Deventhiran K., Kumar M.S., Kumar M.M., Suresh R. (2016). A study on targeted relationships between contractors and consultants in construction industry. Indian Journal of Science and Technology, 9(16), 1-7. https://doi.org/10.17485/ijst/2016/v9i16/92191.
  33. Lam P.T., Wong F.W. (2011). A comparative study of buildability perspectives between clients, consultants and contractors. Construction Innovation, 11(3), 305-320. https://doi.org/10.1108/14714171111149025.
  34. Lehtiranta L., Kärnä S., Junnonen J.M., Julin P. (2012). The role of multi-firm satisfaction in construction project success. Construction Management and Economics, 30(6), 463-475. https://doi.org/10.1080/01446193.2012.669485.
  35. Masengesho E., Wei J., Niyirora R., Umubyeyi N. (2020). Relationship between project consultants’ performance and project success in the Rwandan construction industry. World Journal of Engineering and Technology, 9(1), 138-154.
  36. Mathar H., Assaf S., Hassanain M.A., Abdallah A., Sayed A.M. (2020). Critical success factors for large building construction projects: Perception of consultants and contractors. Built Environment Project and Asset Management, 10(3), 349-367. https://doi.org/10.1108/BEPAM-07-2019-0057.
  37. Mostafavi S.M., Soranj S. (2019). Application of AHP-MCDM method to estimate the delay-time of Tabriz-Bonab highway project. Geotechnical Geology, 15(2), 319-326.
  38. Owusu-Manu D., Addy M.N., Agyekum K., Aidoo C. (2017). Exploring the critical success factors of Ghanaian built environment consulting firms. International Journal of Construction Project Management, 9(2), 137-152.
  39. Peansupap V., Walker D. (2005). Exploratory factors influencing information and communication technology diffusion and adoption within Australian construction organizations: a micro analysis. Construction Innovation, 5(3), 135-157. https://doi.org/10.1108/14714170510815221.
  40. Phua F.T., Rowlinson S. (2004). How important is cooperation to construction project success? A grounded empirical quantification. Engineering, Construction and Architectural Management, 11(1), 45-54. https://doi.org/10.1108/09699980410512656.
  41. Shahbaz S.M., Agrawal S., Pandey M. (2017). Study of Factors Causing Cost Overrun in Construction Industry Using AHP Technique: A Review. International Journal of Engineering Research and Applications, 7(7), 86-88.
  42. Tanujaya B., Prahmana R.C.I., Mumu J. (2022). Likert scale in social sciences research: Problems and difficulties. FWU Journal of Social Sciences, 16(4), 89-101. https://doi.org/10.51709/19951272/Winter2022/7.
  43. Winch G.M. (2012). Managing construction projects. John Wiley & Sons, New Jersey, USA.
  44. Yong Y.C., Mustaffa N.E. (2011). Clients, consultants and contractors' perception of critical success factors for construction projects in malaysia. In: Proceedings of the 27th Annual ARCOM Conference, Bristol, UK, pp. 735, 744.
How to cite
Arjmand, M., Hosseinian, N., & Farshad, S. (2025). Prioritization of Influencing Factors on Interactive Role of Consulting-Contractors in Advancing Project Goals. Civil and Geoengineering Letters, 2(1), e100032. https://doi.org/10.22034/CGEL.2.1.e100032