Prioritizing Factors on Construction Project Claims: A Comprehensive Review
Elham Rezaie1; Ishak Tapan2
- Department of Civil and Construction Management, Istanbul Gelisim University, Istanbul 34300, Türkiye
- Department of Civil and Construction Management, Istanbul Gelisim University, Istanbul 34300, Türkiye
The management of claims in construction projects is a critical aspect of project administration, particularly in the context of increasing complexity and scale of modern construction projects. This comprehensive review synthesizes recent research on factors influencing construction project claims, focusing on studies from various regions including Oman, Vietnam, and Bahrain, and employing methodologies such as fuzzy multi- criteria decision-making, structural equation modeling, and Semantic Network Analysis. Key findings highlight that external risks, client behavior, and unclear project definitions significantly impact claims. The review underscores the importance of proactive management practices and the need for effective documentation and evidence to mitigate claims. The studies collectively emphasize the diverse causes of claims and propose various strategies for improving claims management and reducing project disputes.
Project risk factors, Claim mitigation strategies, Decision-making, Stakeholder analysis, Contract evaluation
The data supporting the findings of this study are available within article. No publicly archived dataset was generated.
This research received no external funding.
- External risks and client behavior drive claims
- Advanced methods improve claim analysis
- Proper documentation reduces disputes and risks
- Abbasi O., Noorzai E., Jafari K.G., Golabchi M. (2020). Exploring the causes of delays in construction industry using a cause-and-effect diagram: case study for Iran. Journal of Architectural Engineering, 26(3), 05020008. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000431.
- Abdel-Khalek H.A., Aziz R.F., Abdellatif I.A. (2019). Prepare and analysis for claims in construction projects using Primavera Contract Management (PCM). Alexandria Engineering Journal, 58(2), 487-497. https://doi.org/10.1016/j.aej.2019.05.001.
- Aibinu A.A., Jagboro G.O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, 20(8), 593-599. https://doi.org/10.1016/S0263-7863(02)00028-5.
- Al-Mohsin M. (2012). Claim analysis of construction projects in Oman. International Journal on Advanced, Science, Engineering and Information Technology, 2, 73-78. https://doi.org/10.18517/ijaseit.2.2.182.
- Amiri M.J.T., Habibzadeh F. (2015). Claim Management in Iran Construction contract (case study: overview of existing risks in Mehr Housing contracts in Tehran). Buletin Teknologi Makanan, 2(6), 315-324.
- Asgari A., Ghorbanian T., Yousefi N., Dadashzadeh D., Khalili F., Bagheri A., Mahvi A.H. (2017). Quality and quantity of construction and demolition waste in Tehran. Journal of Environmental Health Science and Engineering, 15, 14. https://doi.org/10.1186/s40201-017-0276-0.
- Balali A., Moehler R.C., Valipour A. (2022). Ranking cost overrun factors in the mega hospital construction projects using Delphi-SWARA method: An Iranian case study. International Journal of Construction Management, 22(13), 2577-2585. https://doi.org/10.1080/15623599.2020.1811465.
- Bramble B.B., Callahan M.T. (2010). Construction delay claims. Aspen Publishers, Boston, USA.
- Burr A. (2016). Delay and disruption in construction contracts. Informa Law from Routledge, Oxfordshire, England, UK.
- Clough R.H., Sears G.A., Sears S.K., Segner R.O., Rounds J.L. (2015). Construction contracting: A practical guide to company management. John Wiley & Sons, New Jersey, USA.
- Fallahnejad M.H. (2013). Delay causes in Iran gas pipeline projects. International Journal of Project Management, 31(1), 136-146. https://doi.org/10.1016/j.ijproman.2012.06.003.
- Gulezian R., Samelian F. (2003). Baseline determination in construction labor productivity-loss claims. Journal of Management in Engineering, 19(4), 160-165. https://doi.org/10.1061/(ASCE)0742-597X(2003)19:4(160).
- Hai D.T. (2019). Assessment of contractors’ claims on construction projects in Vietnam. The Open Civil Engineering Journal, 13(1), TOCIEJ-13-218. https://doi.org/10.2174/1874149501913010218.
- Halpin D.W. (2010). Construction management. John Wiley & Sons, New Jersey, USA.
- Harris F., McCaffer R., Baldwin A., Edum-Fotwe F. (2021). Modern construction management. John Wiley & Sons, New Jersey, USA.
- Hatami F., Baniasadi M., Sadeghzadeh S. (2015). Prioritizing most important effective factors on contractors' claims in three-factor contracts using phase multi-criteria decision-making methods. International Journal of Advanced Biotechnology and Research, 16(4), 529-539.
- Hosseini M.R., Martek I., Banihashemi S., Chan A.P., Darko A., Tahmasebi M. (2020). Distinguishing characteristics of corruption risks in Iranian construction projects: A weighted correlation network analysis. Science and Engineering Ethics, 26, 205-231. https://doi.org/10.1007/s11948-019-00089-0.
- Hughes W., Champion R., Murdoch J. (2015). Construction contracts: law and management. Routledge, Oxfordshire, England, UK.
- Kazemı F., Adıban E. (2015). Comparing EPC contracts with conventional contracts and their effectiveness on risks of projects in National Iranian South Oil Company. Cumhuriyet Üniversitesi Fen Edebiyat Fakültesi Fen Bilimleri Dergisi, 36(3), 3066-3080.
- Khanzadi M., Sheikhkhoshkar M., Banihashemi S. (2020). BIM applications toward key performance indicators of construction projects in Iran. International Journal of Construction Management, 20(4), 305-320. https://doi.org/10.1080/15623599.2018.1484852.
- Love P.E., Li H. (2000). Quantifying the causes and costs of rework in construction. Construction Management & Economics, 18(4), 479-490. https://doi.org/10.1080/01446190050024897.
- Murdoch J., Hughes W. (2002). Construction contracts: law and management. Routledge, Oxfordshire, England, UK.
- Odeh A.M., Battaineh H.T. (2002). Causes of construction delay: traditional contracts. International Journal of Project Management, 20(1), 67-73. https://doi.org/10.1016/S0263-7863(00)00037-5.
- Saeb A., Danuri M.S.M., Mohamed O. (2021). Selecting the appropriate method for resolving construction disputes in Iran. Iranian Journal of Science and Technology, Transactions of Civil Engineering, 45, 2017-2033. https://doi.org/10.1007/s40996-020-00553-z.
- Samarghandi H., Mousavi S., Taabayan P., Mir Hashemi A., Willoughby K. (2016). Studying the Reasons for Delay and Cost Overrun in Construction Projects: The Case of Iran. Journal of Construction in Developing Countries, 21(1), 51-84. https://doi.org/10.21315/jcdc2016.21.1.4.
- Sambasivan M., Soon Y.W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007.
- Sayareh M., Moodi M.M. (2017). Challenges of risk management and insurance in Iran construction industry. International Journal of Management & Humanities, 2(11), 1-9.
- Shahsavand P., Marefat A., Parchamijalal M. (2018). Causes of delays in construction industry and comparative delay analysis techniques with SCL protocol. Engineering, Construction and Architectural Management, 25(4), 497-533.
- Shen W., Tang W., Yu W., Duffield C.F., Hui F.K.P., Wei Y., Fang J. (2017). Causes of contractors’ claims in international engineering-procurement-construction projects. Journal of Civil Engineering and Management, 23(6), 727-739. https://doi.org/10.3846/13923730.2017.1281839.
- Surahyo A. (2017). Understanding construction contracts. Springer International Publishing, Switzerland.
- Vidogah W., Ndekugri I. (1998). Improving the management of claims on construction contracts: consultant's perspective. Construction Management & Economics, 16(3), 363-372. https://doi.org/10.1080/014461998372385.
- Whitticks E. (2013). Construction Contracts. Elsevier, Amsterdam, Netherlands.
- Zarei B., Sharifi H., Chaghouee Y. (2018). Delay causes analysis in complex construction projects: A semantic network analysis approach. Production Planning & Control, 29(1), 29-40. https://doi.org/10.1080/09537287.2017.1376257.
- Zhi H. (1995). Risk management for overseas construction projects. International Journal of Project Management, 13(4), 231-237. https://doi.org/10.1016/0263-7863(95)00015-I